Precautions For Plastic Crushers

Sep 15, 2024

Leave a message

Before use
1. Before starting, the transmission wheel should be moved by manpower for one or two turns, and the machine can be started only after confirming that the movement is flexible. Wait until the crusher is running normally before feeding.
2. Before stopping the operation, the feeding should be stopped and the materials in the machine should be discharged, and then the power supply of the motor should be cut off.
3. Pay attention to the temperature of the bearing during operation, ensure that the bearing is in a good lubrication state, and pay attention to whether the sound and vibration are abnormal. When an abnormal situation is found, stop to check whether it is stuck by an unbreakable object or whether the machine is damaged.
4. It is necessary to keep the feeding of the crusher uniform to prevent overload. Prevent unbroken objects such as metal and wood from falling into the machine. When it cannot be crushed, the feed moisture should not be too high; In wet crushing, it is necessary to maintain an appropriate amount of water to prevent clogging due to insufficient flushing and reducing production capacity.
5. Check whether the particle size of the crushed product meets the requirements. If there are too many particles that exceed the specified size, the cause should be found out (such as too large gap in the sieve bar, too wide discharge opening, hammer wear, etc.) and appropriate measures should be taken to eliminate them.
6. When the crusher is stopped, check whether the fastening bolts are firm and how much wear is in the parts that are easy to wear. In the case of the tooth crusher, the stop machine should also be used to remove the wood trapped between the teeth.
7. Worn parts should be replaced or repaired in time.
8. The safety device of the crusher should be kept in good condition, and the safety device should not be invalid for the sake of saving trouble.

 

TLP6033-plastic-crusher


After powering on
1. The plastic crusher and the power unit should be installed firmly. If the plastic crusher needs to be fixed for a long time, it should be fixed on the cement foundation; If the plastic crusher needs to flow work, the unit should be installed on the frame made of angle iron, and ensure that the pulley groove of the power engine (diesel engine or electric motor) and the plastic crusher are in the same rotation plane.
2. After the installation of the plastic crusher, check the fastening of the fasteners of each part, and tighten it if it is loose. At the same time, it is necessary to check whether the tightness of the belt is appropriate.
3. Before the plastic crusher starts, turn the rotor by hand to check whether the claw, hammer and rotor are flexible and reliable, whether there is any collision in the crushing room, whether the rotation direction of the rotor is consistent with the direction pointed by the arrow of the machine, and whether the lubrication of the power machine and the plastic crusher is good.
4. Do not replace the pulley casually, in case the speed is too high and the crushing chamber will explode, or the speed is too low to affect the working efficiency of the crusher.
5. After the plastic crusher starts, it should be kept idling for 2~3min, and then feeding after there is no abnormal phenomenon.
6. Pay attention to the operation of the plastic crusher at any time during the work, first of all, the feeding should be uniform to prevent blocking the crushing room; Second, don't overload yourself for long periods of time. If vibration, noise, high temperature of the bearing and the machine are found, and the material is sprayed outward, the machine should be stopped immediately for inspection, and the fault can be eliminated before continuing to work.